Tytuł

Completion of the ring road of the city of Szczuczyn– 2014

The completion of the ‘Construction of the Ring Road of Szczuczyn in the route of the S-61 expressway, s-8 (Ostrów Mazowiecka) – Łomża – Stawiski – Szczuczyn – Ełk – Suwałki – Budzisko – state border (Kaunas), in the section between km 197+550 and km 205+557, together with the construction and redevelopment of the necessary technical infrastructure’. The value of the contract is PLN 102.6 million net (PLN 126 million gross).
The project completion deadline is 15 months, excluding winter periods.

Construction of a ring road of Przemyśl – 2013

Construction of a ring road of Przemyśl, connecting national road no. 28 with Voivodeship road no. 885. The net value of the contract amounts to PLN 72,276,429.75 (the gross Approved Contractual Amount is PLN 88,900,008.59).
The deadline for carrying out the subject of the contract is 16 months from the Commencement Date.

Design and execution of construction works for LCS Łuków – Siedlce, Łuków and Międzyrzecz Podlaski stations for PKP Polskie Linie Kolejowe S.A. - 2012

Design and execution of construction works for LCS Łuków - Siedlce, Łuków and Międzyrzec Podlaski stations (full extent of works), as well as sections of the mainline (only signalling systems and telecommunications) under the OPIE project 'Modernisation of the E 20/CE 20 railway line in the Siedlce–Terespol section, stage II'”.
The value of the contract amounts to: PLN 427,390,878.05 net (PLN 525,690,780 gross). The participation of P.R.I. “POL-AQUA” S.A. in the consortium is 31% (Dragados S.A. – 20%, Vias y Construcciones S.A. – 42%, Electren – 7%).
The deadline for carrying out the object of the contract, i.e. the design and execution of construction works is 35 months from the Commencement Date.

Construction of S8 Expressway A1 (Łódź) section 5 - 2012

The subject of the contract is: "The construction of S-8 express road section Walichnowy interchange – Wrocław (A1), section 5 (Sieradz Południe interchange, no interchange - Łask interchange, no interchange) from km 140+552.05 to km 174+200.00"
The value of the contract amounts to: PLN 1 129 111 686.73 net (PLN 1 388 807 374.68 gross). P.R.I. "POL-AQUA" S.A. holds a 51% share in the consortium. The Consortium Partner - DRAGADOS SA
Realization of the undertaking will consist in a comprehensive implementation of the project, including: road, bridge, cubature and engineering works, including engineering and cubature objects, storm water drainages, sanitary sewerages, environmental protection equipment, road safety equipment, lighting, reconstruction of existing technical infrastructure.
The deadline for performing the subject of the contract was settled to be 27 months from the date of concluding the contract, including also winter periods.

The construction of Świnoujście - Szczecin gas pipeline - 2011

The subject of the agreement consists in a comprehensive execution of the Investment in the General Contracting system (including performance of any Works and obtaining Certificate of Use) regarding the construction of the gas pipeline together with auxiliary infrastructure of DN 800 Świnoujście – Szczecin – high pressure gas pipeline of 80 km, which is located in the following communes (gmina): Świnoujście, Międzyzdroje, Wolin, Stępnica and Goleniów. The Investment includes the construction of the gas pipeline, systems, devices, buildings and roads as well as the performance of any other Works which are required to obtain the certificate of use.
The value of the agreement (flat rate remuneration) amounts to: PLN 146 950 000 net, that is PLN 180 748 500 gross.
The deadline for performing the subject of the agreement (Final Acceptance) was set on 31 January 2013.

Modernization of the fuel system of the Power Plant in Płock for PKN ORLEN S.A. - 2011

Modernization of the fuel system of the Power Plant” in Płock. The scope of the agreement includes: disassembly works and separators, the supply of materials and equipment, assembly works of the Pumping Station No. 1 and No.2 , mechanical commissioning and commissioning itself.
Contract renumeration is 43.9 million złotych (net price).
The contract completion date was set for the 14.07.2014.

Construction of S8 Expressway A1 (Łódź) section 3 - 2011

The subject of the contract is: „Construction of S8 expressway section Syców - Kępno - Sieradz - A1 (Łódź) section 3: Wieruszów - Walichnowy, length -13.1 km”
The value of the contract is 189 809 096.75 PLN net (233 465 189 PLN gross). P.R.I. "POL-AQUA" S.A. share in the consortium is 51%. The Consortium Leader - DRAGADOS SA
Realization of the task will consist in complex realization of the project including: road and engineering works and among them: engineering objects, culverts under S8 expressway, pipe culverts under the transverse and internal roads as well as under the exits, construction of the environment protection elements, modification of drainage infrastructure, construction of storm drainage and road lane drainage, modification and construction of water supply network and construction of sanitary sewage system, modification of power facilities, modification of telecommunication facilities.
The deadline for realization of the contract subject was set for 22 months from the date of beginning of the works, including winter periods.

Construction of S8 Expressway A1 (Łódź) section no 6 and 7 - 2011

The subject of the contract is: "The construction of S-8 express road section Walichnowy road node – Łódz (A1), section 6 (Łask road node – Róża road node) from km 174+200 to km 183+350, section 7 (Dobroń road node – Róża road node) from km 76+479.94 to km 79+800.00"
The value of the contract amounts to PLN 446,809,205.69 net (PLN 549,575,323 gross). P.R.I. "POL-AQUA" S.A. (Consortium Leader)  holds a 51% share in the consortium.The Consortium Partner - DRAGADOS SA
 The execution of the enterprise will consist in a comprehensive execution of the project, which includes: road and engineering works, constructing storm water drainages together with pre-treatment installations and water supply network, execution of traffic safety equipment and lighting, execution of environmental protection equipment including road sewage treatment equipment, acoustic screens, storage reservoirs and animal crossings. Moreover, rebuilding of the existing technical infrastructure will be executed, including: natural watercourses, electricity power lines, telecommunications engineering systems and water supply networks.
The deadline for performing the subject of the contract was settled to be 27 months from the date of concluding the contract, including winter periods.

The construction of residential complex "New Hill Park" in Warsaw - 2011

The subject of the contract is the construction and obtaining the use permit for residential and commercial development "New Hill Park" in Warsaw for MARVIPOL S.A. The deadline for investment was set at 28 February 2013. The contract is worth PLN 39.8 million net.

Reconstruction and expansion of the waste treatment plant in Maszewo – stage II -2011

The agreement provides for the “Reconstruction and extension of the waste treatment plant in Maszewo – stage II” carried out within the project “Wastewater management system in Płock, stage I” co-financed by the European Union from the funds of the Cohesion Fund within the Operational Programme Infrastructure and Environment 2007-2013.
Consideration for the performance of this agreement has been determined at PLN 51,275,915.92 net.
As specified in the tender documentation, the project is to be delivered within 26 months from signing the agreement.

Construction of the principal office of the Gdańsk Shakespeare Theatre 2011

The execution of the project concerns the comprehensive execution of the project: Construction of the principal office of the Gdańsk Shakespeare Theatre" encompassing all the construction work including internal installations, technical infrastructure, communication routes (entries, exits) required to accept the project and put it into use as well as any additional construction and coordination work as required (including coordination of work with the Equipment Provider).
The deadline for completion of the building works has been set for 30.11.2012.
TThe deadline for completing the coordination of the work of the Provider and achieving readiness for acceptance by the General Contractor has been set on 31 December 2012.

Adaptation of Toruń Mills, 2010

Construction of Innovation Centre and Toruń Business Incubator in part of Rychter Mills at Kościuszki street. POL-AQUA will refurbish the building for the price of 28 M PLN, in which the Toruń Business Incubator will start its activity in one year and the Innovation Centre in two years.
The premises dating to the end of 19th and beginning of 20th century will accommodate inter alia: the Innovation Centre, Toruń Technological Incubator, whose adaptation will be carried out by POL-AQUA and International Youth Meeting Centre - recreational=training centre for the youth from all over the world. 
The Innovation Centre is an interactive museum, where the visitors will be able to learn various areas of science through play, experiment, participation in the experiments' and own observations.
Toruń Technological Incubator is a place, where the businessmen will be able to enjoy the benefits of state of the art technologies and the latest scientific achievements.

Office Building "Wilanów Office Park", Warsaw 2010

Execution of the project in the capacity of the general contractor of class B+ office building for POLNORD S.A. The subject of the Agreement concerns the execution of the building works concerning the construction on the plot of "B1" office building in basic standard, with 3 office storeys above the ground and 2 underground storeys accommodating the garages and technical premises, including the finishing, road-network infrastructure, land development, based on the Design.
The completion date of the subject of the agreement including all the acceptances and obtaining the occupancy permit has been set for 17 months starting from 1 February 2011.
The fixed remuneration for the execution of the subject of the agreement has been set at the level of 37 988 994 PLN net.

Construction and reconstruction of selected parts of the sewage network in the catchment area of sewage treatment plat GIGABLOK in Katowice, 2010


Execution for Katowice Water Supply-Sewage Infrastructure of the project concerning the construction and reconstruction of selected parts of the sewage network in the catchment area of sewage treatment plat GIGABLOK in Katowice.
The execution of the entire project planned by the Procuring Authority was divided into 9 parts, which were the subject of separate tenders entered by the Company.  POL-AQUA will execute part 3 through 9, which concern the appropriate areas of Katowice streets.
The date of completion of the works inclusive of the period necessary to obtain occupancy permit by the Procuring Authority is from 11 to 28 months, depending on the specific area of the part being carried out.
The total value for the individual parts of the tasks is PLN 73 626 696.22 gross.This is yet another investment of POL-AQUA S.A. in southern Poland.

Construction of wastewater transmission system from left-bank Warsaw to Czajka WWTP – stage II by Vectra S.A., 2010

Construction of wastewater transmission system from left-bank Warsaw to Czajka WWTP – stage II, - in scope of execution of left-bank collecting pipes together with building facilities and network crossing the route of Northern Bridge near Marymoncka interchange with connection and cascade chamber near Farysa street.
There shall be executed with applying the microtunnelling technology, within the scope of the investment project, a collecting pipe with a diameter of 2.8 m and 1,200 m long, 200m long collecting pipe in the open excavation, as well as 4 complicated underground facilities to connect with the existing collecting pipes and to control the waste water flow to the future sewer under the Vistula river. The above-mentioned diameter of the collecting pipe of 2.8 m is at present the biggest diameter executed with applying of microtunnelling technology up to now in Poland.
The gross lump sum remuneration of the Contractor amounts to PLN 91 500 000. The completion term is settled to August 31st, 2010.


North Bridge, Warsaw 2009

Construction of a 3.4 km long access route and a 796 m bridge between Pułkowa and Modlińska streets in Warsaw. The project includes adaptation of the entire underground infrastructure and reconstruction of all neighboring roads (together with embankments, road surface, on-ground infrastructure, pile driving), building north and south roads (three lanes in each direction, overpasses, flyovers, tunnels, pedestrian bridges, etc.), building the support structure of the car and tramway bridge along with a pedestrian and bike route. The contract value exceeds PLN 976 million gross.

Construction of right-bank collector in Poznań, 2009

Execution by the Consortium of the waste water collecting pipe and storm water collector in Poznań. Construction of right-bank collector II in Poznań is another contract of P.R.I. „POL-AQUA” S.A. connected with non-excavating technologies. Within the scope of the Contract with applying of microtunnelling technologies, there shall be executed the collecting pipes with diameters from 0.6 m to 2.4 m. The Contract’s execution period is 24 months since the date of signing of the Contract with an option to shorten the completion period. The total net contract price is PLN 84,492,169.31 (gross: PLN 103,080,446.56).

Construction of the infrastructure for „Warsaw Airport Business Park”, Warsaw 2009

Execution of designing and realisation (construction) of the infrastructure facilities, separately for executed and taken-over facilities i.e.: utilities of the land and roads, for the planned by the Investor buildings complex under the name of „Warsaw Airport Business Park” located in Warsaw, at 2B. Żwirki i Wigury Street. The contract’s execution period is 30 months.
The total net lump sum remuneration of the Company (according to preliminary estimation) amounts to PLN 50 million.

General overhaul and modernisation of Kielce University of Technology 2009

The works shall be financed by the Operational Programme of Eastern Poland Development – Modern Economy. It is the first investment of this kind in this region. There shall be started, within the confines of MODIN II, a general overhaul and modernisation of four didactic buildings A; B; C; D; including passages and laboratory halls No. 1; 2; 3; 4; together with the connectors.
Net value of the contract amounts to over PLN 46 million.

AUCHAN – Commercial and Service Centre at Łomianki 2009

General execution of the Auchan Commercial and Service Centre at Łomianki including technical infrastructure and internal roads and car parks. The net value of the contracts is over PLN 107 million.

"Sarnia Dolina 2" housing estate, Gdańsk 2009

Execution as a General Contractor of the "Sarnia Dolina 2" housing estate in the plots located at Lublewo, Jankowo and Bąkowo (Kolbudy municipality) near Gdańsk. The net value of the contracts is over PLN 116 million.

Engineering works at OKĘCIE International Airport, Warszawa 2009

Execution of the engineering works, as a subcontractor of TEERAG - ASDAG POLSKA Sp. z o.o., including execution of water mains, dewatering of road corps and microtunnelling in scope of the order under the name of: "Construction of S-2 express way, Konotopa - Puławska section, including the connection with OKĘCIE International Airport and Marynarska Street (S-79) in Warsaw. The net value of the contracts is over PLN 59 million.

AUCHAN Commercial and Service Centre, Gliwice 2009

General Contractor for AUCHAN Commercial and Service Centre in Gliwice including accompanying infrastructure. The Contract includes general execution of construction works – internal system and rebuilding of the external traffic system (external system). The net value of the contracts is PLN 133 million.

"Wilanów Office Park" office building, Warsaw 2009

General Contractor of the execution of the office building, A class, being a part of the investment project under the name “ Wilanów Office Park”. The scope of construction works in particular includes the execution of the office building with three overground and two underground storeys with finishing works and roads and networks infrastructure as well as land development and acquiring the usage permit. The gross value of the contracts is PLN 60 million.

 

Siekierkowska Route, Warsaw 2008

Project name: “Construction of the Siekierkowska Route – intersection of the National Road No. 2 with the Siekierkowska Route”, i.e. the section between Idzikowskiego and Wał Zawadowski streets. The engineering and construction work covers: road and bridge work, reconstruction of water mains, construction of rain water and general purpose collector network, reconstruction of the gas network, construction and reconstruction of power and telecommunications infrastructure, construction of the road lighting and traffic light systems, noise screens, designing greeneries, providing traffic safety and organizational solutions, as well as positioning elements of the City Information System. Contract value – in excess of PLN 124 million gross.

The National Stadium, Warsaw 2008

Executing the first stage of the project related to preparing the site for a multifunctional National Stadium. 200 days for performing demolition work, ground work and stabilizing the soil on which the new stadium will be erected.
The scope of construction work covers the following:

  • demolition of the old facility and transporting various types of rubble off site,
  • ground work, including: digging trenches (and transporting some of the soil and waste off site), constructing embankments,
  • fencing the construction site,
  • soil strengthening (also by pile driving)

The contract value exceeds PLN 125 million gross

Constructing the second roadway of Al. Wilanowska, Warsaw 2008

Performing, within a consortium made up of: P.R.I. POL-AQUA” S.A. and Budownictwo Drogowe „ALTKOM” Sp. z o.o., construction work related to building the second roadway of Al. Wilanowska between Sobieskiego and Dolina Służewiecka streets in Warsaw.
The contract value exceeded PLN 50 million gross.

Sewer network for the REGATY Residential Estate, Warsaw 2008

Building a gravity sewer pipeline with the diameter of 800 mm between the intersection of Kobiałka street in Warsaw and the Regaty Residential District access road to the Płudy pumping station at Orchowiecka street in Warsaw. The project was commissioned by Dom Development S.A.
The contract value exceeded PLN 40 million net.

JEZIORAK Shopping Mall, Iława 2008

Construction of the "Jeziorak" Shopping Mall in Iława: designing, supplying, installing and assembling individual elements of the facility, as well as eliminating all defects. The contract value exceeds PLN 38 million net.

"Nowe Bielany" Residential and Service Center, Warsaw 2008

Acting as the general contractor, performing construction and installation work for the 1st stage of the “Nowe Bielany” Residential and Service Center, including an underground car park, roadways, technical connections and site arrangement at Kasprowicza/Nocznickiego streets in Warsaw. The contract value exceeds PLN 56 million net.

Pipeline for Grupa LOTOS S.A., Gdańsk 2008

Construction of a pipeline in Gdańsk, connecting the LOTOS Refinery with fuel installations on the premises of the North Port. The pipeline length is 11 km, with 400 m constructed with the use of a controlled drill method under the bed of the Martwa Wisła river. The contract value is nearly PLN 40 million net.

“Kraków Business Park” office complex, Zabierzów 2008

Erecting office buildings - Kraków Business Park 800 and Kraków Business Park 1000 at Krakowska street in Zabierzów. The scope of work included the following: performing all preparation work necessary to commence and complete the construction stage, draining the construction site, performing all the necessary work consisting in removing or protecting all existing trees; performing all necessary ground work, erecting the building, finishing it, providing utility connections, etc.
The contract value exceeded PLN 128 million net.

„Sosnowa Dolina” Residential Estate, Słomin 2008

Completing the „Sosnowa Dolina” Residential Estate in a raw, unfinished condition, in the village of Słomin, the gmina of Raszyn. The engineering work we have been entrusted with included, inter alia, ground work, preparing the site for construction work, foundations, insulation, complete sanitary and rain water systems, water mains, a water treatment station, as well as pipelines for transferring treated wastewater. The contract also covers comprehensive road work and soil replacement.
The contract value exceeds PLN 25 million net.

AUCHAN Shopping Center, Szczecin 2007

Our company was the general contractor of the Auchan Szczecin Shopping Center, along with the accompanying infrastructure. The contract covers general contractorship for outdoor facilities, including:

  • road work, engineering facilities, telecommunications and technical networks, power grid, water distribution mains, process water system, medium-pressure gas network, waste water system, rain water system, as well as temporary site arrangement,

as well as indoor facilities, such as:

  • site arrangement, completing the raw state under roof, building indoor systems and finishing the indoors.

The contract value exceeds PLN 50 million net.

Water mains and sewer network, Zabrze 2007

“Improvement of the water and waste water management system in the gmina of Zabrze – districts of Zaborze, Makoszowy and Biskupice – stage I”. The scope of work provides for constructing a wastewater and rain water collector system, along with the reconstruction of connections and elements of the roadway in the Koziołka district in Zabrze - Biskupice.
The contract value exceeds PLN 27 million gross.

Apartment District, Gdańsk 2007

Construction of residential buildings along with the infrastructure – Apartment District at Szafarnia street in Gdańsk. The scope of work covers performing, as the general contractor, all the work required to complete the project and to commission it for use. The contractor is also obliged to obtain the commissioning permit, make the entry in the premises and buildings register, and obtain individual land and mortgage register entries for the apartments.
The contract value exceeds PLN 92 million net.

Apartment block , Warsaw 2007

Acting as the general contractor for construction of an apartment block at Emilii Plater street in Warsaw. The scope of work covers erecting a 9-storey apartment building with an office and service section and an underground car park, as well as completing all communications and utility systems in the building.
The contract value exceeds PLN 39 million net.

Fuel pipeline, Ostrów Wielkopolski – Wrocław 2007

Construction of a fuel pipeline between Ostrów Wielkopolski and Wrocław, along with the technical infrastructure facilities, to the order of PKN ORLEN S.A.. The project covers construction of a 110 km section of the DN250 pipeline, together with the technical infrastructure facilities, mechanical start-up, launch and commissioning of the system.
The contract value exceeds PLN 47 million net.

TESCO Hypermarket, Gdańsk 2007

Acting as the general contractor for the construction of the TESCO hypermarket in Gdańsk-Chełm. The construction work covers the following: ground work, construction, internal systems, finishing, arranging the site, providing the designs and eliminating all post-construction defects.
The contract value is nearly PLN 92 million net.

Sewer network, Otwock 2007

Designing and constructing a sewer network in the gmina of Otwock, commissioning the sanitary and gravity systems, pressure lines, pumping stations and connections, as well as modernizing the collector transporting wastewater to the waste water treatment plant.
The contract value exceeds PLN 105 million gross.

Iron Foundry, Elbląg 2007

Constructing the Iron Foundry in Elbląg.
The project covers all construction work for the facility itself and for the entire accompanying infrastructure. The construction work is divided into two stages:

  • construction of the buildings
  • finishing and installations work

The contract value exceeds PLN 43 million net.

Restaura Górskiego, Warszawa 2007

Acting as the general contractor for complete restoration of Restaura Górskiego, an exclusive apartment block in downtown Warsaw (Górskiego 6 street), to the order of the Restaura company. Performing construction and installation work, including preparation of technical documentation for sheet pile walls and coordination of work carried out by the ordering party’s subcontractors, as well as coordinating deliveries made by his suppliers.

The contract value exceeds PLN 68 million net.

Fuel Depot No.5, Emilianów 2007

Construction of four fuel storage tanks with the capacity of 10,000 m3 each, along with the accompanying infrastructure in the Fuel Depot No.5 in Emilianów. The contract value exceeds PLN 33 million net.

Sewer network, Radom 2007

Modernization of the sanitary sewer network in the gmina of Radom. Work related to reconstruction and modernization of the sewer network, rain water collector and water mains for the city of Radom. The project co-financed by the European Union’s Cohesion Fund. The contract value exceeds PLN 9 million net.

Turbine expander, Police 2007

Replacing the existing 1st degree reduction system by a turbine expander in the Chemical Plant in the town of Police. The contract value is nearly PLN 8 million net.

Water mains and sewer network system for ”Miasteczko Wilanów”, Warsaw 2007

Constructing the sewer system and the rain water collector, as well as the water mains for "Miasteczko Wilanów". Constructing the sewer under Królowej Marysieńki-bis, Sobieskiego-bis and Projektowana 9 streets.
The contract value exceeds PLN 3 million net.

Storage depot, Wierzbno 2007

Designing and constructing a crude oil storage depot constituting part of a project titled “Forwarding Terminal and a Connection to PERN", in the vicinity of Wierzbno in the gmina of Przytoczna.
The contract value is nearly PLN 17 million net.

Mysłowice - Brzezinka pipeline, 2007

Performing, to the order of PGNiG, the project titled: “Construction of a DN500 CN 4,0MPa L=3280m DN 200 CN 2,5MPa L=2830m Mysłowice – Brzezinka pipeline”.
The contract value is nearly PLN 7 million net.

Adamowo - Plebanka pipeline 2006

Construction of the ST1 Adamowo – BS Plebanka pipeline, including installation of the linear portion of the pipeline along with cathodic protection, natural and artificial passage ways, such as roads, rivers, and construction of a fiber optic network in the gmina of Repki and the town of Węgrów in the Mazowsze province. Particular emphasis was put on the following:

  • devising a process-oriented test method for conducting strength and leak tightness tests of the DN 800 pipeline, pipe III, and conducting strength and leak-tightness tests of the ST1 Adamowo¬-Plebanka pipeline.
  • assembling the DN 800-PN 6,3 MPa pipeline along with natural and artificial passage ways in Węgrów
  • preparing the SZ 110, SZ111, SZ 120, SZ 130, SZ 140, SZ 150 and SZ 151 lock stations
  • The contract value exceeds PLN 14 million net.

Sewer network, Lewin Brzeski and Skarbimierz 2006

    Construction of the sewer network in the gminas of Lewin Brzeski and Skarbimierz in the Opolskie province.
    The contract value is nearly EUR 10 million net.

Improving water management in the gmina of Sosnowiec 2006

    Modernizing the Radocha II waste water treatment plant and constructing the Bobrek collector, under the “Sosnowiec waste water management” project. The scope of the order covers modernization of the waste water treatment plat to increase its capacity by 35,000 m3/day and construction of a 15 km long waste water collector made of gravity- and pump-powered sections.
    The contract value is nearly EUR 22 million net.

Local sewer network, Wrocław 2006

    Expansion of a local sewer network – Stage II (Wojszyce and Partynice, Krzyki Południe, Klecina). The contract value exceeds EUR 14 million net.

Cooling tower tank in the Łagisza Power Plant, Będzin 2006

    Performing ground work in preparation for construction of a cooling tower tank in the Łagisza Power Plant, as well as carrying out drainage work in the Turbine Section of the 460 MW unit. The contract value exceeds PLN 5 million net.

Fuel storage tanks, Kawice 2006

    Constructing two fuel storage tanks with the capacity of 10,000 m3 each, along with the accompanying infrastructure.
    The contract value is nearly PLN 13 million net.

Water mains and sewer network, Tychy 2006

    Constructing waste water and rain water systems in the Czułów district in Tychy.
    The contract value exceeds EUR 16 million net.

Warsaw F.Chopin Airport, Warsaw 2006

    Constructing storage reservoirs along with flow adjustment chambers and reconstruction of the rain water collector system in the vicinity of the end of runway 33 DS-3 at Warsaw’s F.Chopin Airport.
    The contract value is nearly PLN 12 million net.

Pipeline and fiber optic line in the gminas of Korytnica and Dobre 2006

    Constructing the DN 800/pn 6,3 MPa pipeline with cathodic protection, and a fiber optic line in the gminas of Korytnica and Dobre.
    The contract value exceeds PLN 15 million net.

GALERIA BIAŁA Shopping and Service Center, Białystok 2006

    Preparing the design and constructing the Galeria Biała Shopping and Service Center in Białystok. A turn-key project.
    The contract value exceeds PLN 145 million net.

IKEA Shopping Center, Warsaw Targówek 2005

    A full range of ground work – macro leveling of land and replacement of soil. Preparing the site (excavation and transporting 110,000 m3 of soil off site, as well as delivering and laying 326,000 m3 of soil).
    The contract value is nearly PLN 16 million net.

OUTLET Fashion House, Piaseczno 2005

    Making arrangements, preparing designs and constructing DN 250 mm water mains with the total length of approximately 1,000 m, as well as a DN 200-600 mm waste water and rain water collector with the total length of approx. 4,000 m.
    The contract value exceeds PLN 3 million net.

3rd line of the “Przyjaźń” Pipeline 2005

    A full range of specialist engineering, construction and installation work for a DN 800 crude oil pipeline in the gminas of Bulkowo, Sokołów, Liw, Załuski, Naruszewo and Bodzanów – total length approx. 65,000 meters.
    The contract value exceeds PLN 18 million net.

AUCHAN Shopping and Service Center, Sosnowiec 2005

    Reconstruction and construction of the roadway system, sewer network, rain water collector, power grid – on the premises of the Auchan Shopping and Service Center in Sosnowiec (Śląskie voivodeship).
    The contract value exceeds PLN 15 million net.

Water mains and sewer network, Jelenia Góra 2005

    Performing the project: Provision of water and collection of waste water in Jelenia Góra. Construction of the water mains and sewer network.
    The contract value is nearly EUR 6 million net.

Construction of the sewer network in the gminas of Lubsza, Oława and Olszanka 2005

    Constructing a sewer network in the gminas of Lubsza, Oława and Olszanka. Building a power connection for the pumping station at Cegielniana street in Brzeg, and constructing supplemental sewer system elements in the gminas of Lubsza and Olszanka.
    The contract value exceeds EUR 11 million net.

Waste water treatment plant, Stare Babice 2005

    Expansion of a waste water treatment plant and construction of a sewer network in the gmina of Stare Babice in the Mazowsze voivodeship.
    The contract value exceeds PLN 21 million net.

Natural gas pumping station, Ciechanów 2004

    Performing installation, engineering, construction, process-related and electrical work. Constructing a waste water pumping station, as well as a biological waste water treatment plant, a sewer system and a water mains. Specialist work related to land drainage, construction of roads, sidewalks and on-site yards. The work was carried out in compliance wit a very strict quality assurance system, and vast majority of that work was performed in explosion zones. Apart from construction of facilities closely related to gas compression, auxiliary facilities were erected as well, such as turbo compressor control rooms, reduction and metering stations, water main, sewer systems and power lines, access roads, maneuvering yards, etc.
    The contract value exceeds PLN 10 million net.

3rd line of the “Przyjaźń” pipeline 2004

    Performing a full range of engineering, construction and installation work related to the 3rd line of the “Przyjaźń” Pipeline between ST-1 Adamowo - Plebanka Depot in the gminas of Liw, Bulkowo and Sokołów Podlaski in the Mazowsze voivodeship.
    The contract value exceeds PLN 41 million net.

GALERIA MOKOTÓW Shopping Mall, Warsaw 2004

    Constructing part of the infrastructure for the Fort Mokotów Residential Estate. Constructing DN 100-200 mm water mains with the length of approx. 3,200 m, DN 160-800 mm sewer with the length of approx. 2,400 m, and a DN 200-600 rain water collector with the length of approx. 6000 m. In addition – roads, parking lots, unloading yards and sidewalks. The contract value exceeds PLN 18 million net.

ZŁOTE TARASY Shopping Mall, Warsaw 2002

    Comprehensive ground work consisting in macro leveling of terrain, excavation work and transporting 360,000 m3 of soil off-site. The facility is located in downtown Warsaw – not only in the geographical, but also in the business center of the city – it is here that the largest and most modern properties are situated. Złote Tarasy Shopping Mall is a complex of offices, shopping malls and entertainment centers that has become a characteristic, easily recognizable landmark of the capital city. While performing the ground work consisting in constructing outdoor systems of the facility, POL-AQUA had to take into consideration the close proximity of Warsaw’s Central Railway Station, large buildings, as well as heavy pedestrian and vehicle traffic. The need to comply with strict city regulations related to performing construction work in the very heart of the city posed an additional difficulty.

ARKADIA Shopping Center, Warsaw 2002

    Performing all work related to the outdoor infrastructure of the Arkadia Shopping Center. Constructing the DN 300 mm water mains with the length of 1,490 m, a DN 160-600 mm sewer with the length of 9,940 m and a DN 80-250 mm heating pipeline with the length of 1,109 m. Road construction: reconstruction of roadways, parking lots, sidewalks and the tramway power lines.
    The Arkadia is Poland’s largest shopping, service and entertainment center constructed in the years 2002-2004. The value of the entire project equaled approximately EUR 270 million. Our company was entrusted with performing the duties of the general contractor and designer of the outdoor infrastructure for this unmatched-size facility. Due to the extraordinary nature of the project, POL-AQUA had to act in a comprehensive manner, taking care of both formal and execution-related duties.

 
POLAQUA Mostostal Wyroby betonowe TECO